'Builder is always bound to pay compensation for delay'
The Free Press Journal|November 25, 2024
If the builder does not deliver the flat to the home buyer as per agreed timelines what relief does RERA offer? What action can be taken against the builder?
Shirish V Deshpande

Ashish Taskar, Thane RERA has established that time is of the essence in agreements for sale, requiring both the builder (promoter) and homebuyer (allottee) to adhere to agreed timelines. If the homebuyer delays installment payments, they must pay interest on the defaulted amount at the prescribed rate. Conversely, if the promoter fails to deliver possession on time, the homebuyer has two options: withdraw from the project or continue despite the delay.

In case of withdrawal due to delay, section 18(1) mandates that the promoter refund the entire amount paid by the homebuyer, along with interest at marginal cost of fund-based lending rate (MCLR) + 2% per annum, calculated from the dates the payments were received to the date of refund.

Additionally, the promoter must compensate for losses incurred by the homebuyer. Section 19(4) reinforces the homebuyer's right to a full refund with interest and compensation.

هذه القصة مأخوذة من طبعة November 25, 2024 من The Free Press Journal.

ابدأ النسخة التجريبية المجانية من Magzter GOLD لمدة 7 أيام للوصول إلى آلاف القصص المتميزة المنسقة وأكثر من 9,000 مجلة وصحيفة.

هذه القصة مأخوذة من طبعة November 25, 2024 من The Free Press Journal.

ابدأ النسخة التجريبية المجانية من Magzter GOLD لمدة 7 أيام للوصول إلى آلاف القصص المتميزة المنسقة وأكثر من 9,000 مجلة وصحيفة.

المزيد من القصص من THE FREE PRESS JOURNAL مشاهدة الكل
HOoABL buys US centre's landmark SoBo property
The Free Press Journal

HOoABL buys US centre's landmark SoBo property

Mumbai-based real estate firm House of Abhinandan Lodha (HOABL) has bought the American Center located at Marine Lines for Rs56 crore.

time-read
1 min  |
December 01, 2024
Activists call for renewed push
The Free Press Journal

Activists call for renewed push

WORLD AIDS DAY | State's progress in curbing fresh HIV infections slows; experts seek stronger public-private partnerships, expanded outreach efforts

time-read
2 mins  |
December 01, 2024
The Free Press Journal

3 held for duping lk women with ration scheme

The Nizampura police have arrested three men for allegedly duping over 1,000 women by promising to give them ration for a year for Rs500 each.

time-read
1 min  |
December 01, 2024
The Free Press Journal

Dumper mows down labourer in Kandivali

A 30-year-old man was killed in an accident in Kandivali (East) on Friday, November 29.

time-read
1 min  |
December 01, 2024
The Free Press Journal

Crematorium closed for traditional cremations

The crematorium in Andheri's Amboli will be shut for traditional services from December 1 onwards due to repair work undertaken by the BMC.

time-read
1 min  |
December 01, 2024
Paralytic Mathadi leader can drive after stem cell process
The Free Press Journal

Paralytic Mathadi leader can drive after stem cell process

New procedure offers hope to patients who cannot undergo traditional blood transfusions

time-read
1 min  |
December 01, 2024
4 horses made to race on highway sent to PETA India
The Free Press Journal

4 horses made to race on highway sent to PETA India

Four horses forced to illegally race on the Western Express Highway in June were recently handed over to the People for the Ethical Treatment of Animals (PETA) under interim custody.

time-read
1 min  |
December 01, 2024
The Free Press Journal

HC imposes ₹5 lakh cost on petitioner for frivolous plea

The Bombay High Court has imposed a Rs5 lakh cost on a petitioner for filing a baseless writ petition in a land dispute related to Kolhapur Airport.

time-read
1 min  |
December 01, 2024
The Free Press Journal

ICICI Lombard found guilty of wrongfully rejecting claim

Transport firm awarded 75% of claimed amount of ₹2.5L along with ₹10,000 towards litigation costs

time-read
2 mins  |
December 01, 2024
Dharavi sports club in a mess
The Free Press Journal

Dharavi sports club in a mess

UNSPORTING BEHAVIOUR | Members allege mismanagement and lack of amenities despite hefty fees; original remit to develop local talent ignored

time-read
2 mins  |
December 01, 2024