A Narrow Gauge Railway Under South London
The Railway Magazine|January 2018

Keith Fender reports on the construction of the Northern Line extension to Battersea, which has necessitated the construction of a narrow gauge railway under south London – albeit a temporary one.

A Narrow Gauge Railway Under South London

MAJOR tunnelling projects are normally accompanied by construction railways using locos designed for mining and tunnelling – by their nature these railways are temporary and rarely documented in the railway press. Thanks to a visit to see construction work on the new Northern Line Extension (NLE) in south London, The Railway Magazine can tell the story of one short-lived, 750mmgauge railway under Battersea and Kennington that began operation in 2017. By the middle of 2018 it will no longer exist… although another new one will be in operation nearby.

The NLE project

The 3km, £1billion extension of the Northern Line from Kennington to a new terminus at Battersea Power Station is designed to serve one of the biggest regeneration projects in London, with more than 20,000 new homes, new offices, and the imposing new American Embassy being built in the area – part of which was once home to the LSWR’s Nine Elms shed.

The new Underground line, which is being partly paid for by the developers building the new homes and offices, is due to open in late-2020. Two new Zone 1 stations will be added to the Northern Line – Battersea Power Station and Nine Elms.

A 50-50 joint venture consortium, comprising Spanish civil engineering firm Ferrovial Agroman and UK construction company Laing O’Rourke, is building the new line – the consortium is known as FLO (Ferrovial Agroman/Laing O’Rourke). Two separate tunnels have been created by two tunnel boring machines (TBMs) between January and November 2017.

Both new tunnels join the Northern Line just south of Kennington station, with separate junctions for both being off the Kennington empty stock loop line, sections of which will become part of the new Battersea branch.

Esta historia es de la edición January 2018 de The Railway Magazine.

Comience su prueba gratuita de Magzter GOLD de 7 días para acceder a miles de historias premium seleccionadas y a más de 9,000 revistas y periódicos.

Esta historia es de la edición January 2018 de The Railway Magazine.

Comience su prueba gratuita de Magzter GOLD de 7 días para acceder a miles de historias premium seleccionadas y a más de 9,000 revistas y periódicos.

MÁS HISTORIAS DE THE RAILWAY MAGAZINEVer todo
Ro-railers Ahead Of Their Time Or Overtaken By Events?
The Railway Magazine

Ro-railers Ahead Of Their Time Or Overtaken By Events?

A new type of vehicle for use on both road and rail was trialled in the early 1930s, but never caught on. Alan Dale considers whether early road-rail vehicles were too advanced for their time.

time-read
8 minutos  |
February 2018
From Upminster To Upcycled: Vivarail's D-train
The Railway Magazine

From Upminster To Upcycled: Vivarail's D-train

Ben Jones visits Long Marston to find out how redundant District Line trains are being rebuilt to provide cheaper and greener alternatives to brand new multiple units – and how Vivarail is looking to the future with new methods of propulsion.

time-read
7 minutos  |
February 2018
Fatal Fracture
The Railway Magazine

Fatal Fracture

In the fourth of our series looking back at major railway accidents, Fraser Pithie recalls what was a terrible accident in terms of loss of life – an event that took place 50 years ago, in 1967. Much was learnt from the tragic and profound events that arose from a fateful Bonfire Night at Hither Green, London on what was then British Rail’s Southern Region.

time-read
10+ minutos  |
November 2017
ECML Power Supply Upgrade Complete
The Railway Magazine

ECML Power Supply Upgrade Complete

THE first phase of Network Rail’s programme to upgrade 25kV AC power supplies on the East Coast Main Line (ECML) is on track for completion in time for the introduction of new train fleets in 2018.

time-read
2 minutos  |
November 2017
Tyseley Launches £3million Share Offer For New TOC
The Railway Magazine

Tyseley Launches £3million Share Offer For New TOC

FROM the moment Tyseley unveiled its newly overhauled flagship locomotive No. 7029 Clun Castle at the end of October, fans of the Collett 4-6-0 began to ask when the famous BR(W) ‘Castle’will double-head with sister No. 5043 Earl of Mount Edgcumbe on the main line.

time-read
4 minutos  |
January 2018
Bredgar's Little Gem
The Railway Magazine

Bredgar's Little Gem

Gareth Evans visits the Bredgar & Wormshill Railway to discover the latest developments at the 2ft-gauge line in Kent, run by a group of friends, and open once a month to the public. 

time-read
10+ minutos  |
January 2018
South Yorkshire Tram-Train Project 400% Over Budget
The Railway Magazine

South Yorkshire Tram-Train Project 400% Over Budget

South Yorkshire Tram-Train Project 400% Over Budget

time-read
2 minutos  |
August 2017
Rebirth Of The Corris Railway
The Railway Magazine

Rebirth Of The Corris Railway

In the latest instalment of our periodic Lazarus Lines features Cliff Thomas describes the resurrection the Corris Railway, previously owned by the GWR and Nationalised in 1948.

time-read
10+ minutos  |
August 2017
Tornado Hits Cornwall
The Railway Magazine

Tornado Hits Cornwall

In a P&P extra, Keith Farr rides behind ‘A1’ No. 60163 Tornado on an epic journey from London to Cornwall – the first visit of the class to the Duchy.

time-read
9 minutos  |
August 2017
Steam & Heritage
The Railway Magazine

Steam & Heritage

Thousands at Mid-Hants for gala marking 50 years since Southern steam bowed out

time-read
3 minutos  |
August 2017