Bridging the Gap between Construction and Operations
Commercial Design|October 2020
Matthew Smith, Associate Head of the School of Energy, Geoscience, Infrastructure and Society at Heriot-Watt University Dubai, explains how FM firms can streamline operations before ground is ever broken on a project.
Bridging the Gap between Construction and Operations

Upon handover, facility managers are often at the receiving ends of occupants’ grievances and system failures. But why is that so?

This is because once a building is conceptualised and constructed, it is often handed over to the facilities team without sufficient testing, training, operating procedures and maintenance manuals that are required to manage a large, complex network of interdependent systems.

The ground reality is that most FM operators are kept at bay during the design and construction phases and are eventually introduced to the project only during the time of handover.

The incomplete building is then passed on to the facilities team with multiple contractors scrambling to wind up the project, tie up loose ends, finish moving furniture and boxes, and settle tenants in.

In such a scenario, FM operators could potentially mismanage many critical priorities – such as slotting in the equipment information into their monitoring and maintenance management system, programming maintenance schedule, recording operating procedures, and drawing up service agreements – that prove to be disruptive in the future.

Although we see a steady integration of FM professionals at the early stages of a construction project, there is more potential to ensure that the FM team is fully capable and ready to efficiently run and maintain the facility in the long-term.

Here we discuss how and why FM consultants can help bridge the gap between construction and FM operations with a smooth and problem-free handover.

Integrate early

The ideal first step is to bring in FM consultants and operators to the table right from the onset so they can add value with their expertise and factor in FM needs.

Bu hikaye Commercial Design dergisinin October 2020 sayısından alınmıştır.

Start your 7-day Magzter GOLD free trial to access thousands of curated premium stories, and 9,000+ magazines and newspapers.

Bu hikaye Commercial Design dergisinin October 2020 sayısından alınmıştır.

Start your 7-day Magzter GOLD free trial to access thousands of curated premium stories, and 9,000+ magazines and newspapers.

COMMERCIAL DESIGN DERGISINDEN DAHA FAZLA HIKAYETümünü görüntüle
SYNQ.WORK PLANS TO INVEST 60 CR. TO ADD 6 LAKH SQ. FT. OF MANAGED OFFICE SPACES TO ITS PORTFOLIO WITH NEW CENTRES IN BANGALORE, PUNE, AND HYDERABAD
Commercial Design

SYNQ.WORK PLANS TO INVEST 60 CR. TO ADD 6 LAKH SQ. FT. OF MANAGED OFFICE SPACES TO ITS PORTFOLIO WITH NEW CENTRES IN BANGALORE, PUNE, AND HYDERABAD

Synq.work, one of the leading managed office space providers in India has recently made an announcement to expand the current seating capacity from 3200 to 12,000 by adding an additional 8800 seats by December 2025.

time-read
1 min  |
September 2024
TANGIBLE ROI
Commercial Design

TANGIBLE ROI

How to connect your CAFM to obtain tangible ROI

time-read
3 dak  |
September 2024
UNLEASHING THE POTENTIAL OF THE OFFICE CAMPUS
Commercial Design

UNLEASHING THE POTENTIAL OF THE OFFICE CAMPUS

Exciting concept can re-ignite employees' desire to work onsite and drive creativity

time-read
2 dak  |
September 2024
REINVENTING RETAIL
Commercial Design

REINVENTING RETAIL

Inside Culdesac's future-forward design of Bershka Valencia

time-read
2 dak  |
September 2024
A VISION BEYOND THE CONVENTIONAL
Commercial Design

A VISION BEYOND THE CONVENTIONAL

Kangana Ranaut's Manikarnika Films Studio office, designed by The Orange Lane, transforms a creative workspace into an inspirational sanctuary, masterfully blending tranquillity and innovation.

time-read
2 dak  |
September 2024
WHEN INDUSTRIAL CHIC MEETS URBAN OASIS
Commercial Design

WHEN INDUSTRIAL CHIC MEETS URBAN OASIS

Studio Lotus breathes new life into Chennai's largest IT park with the design of The Hub at DLF Cybercity, Chennai - a dynamic mixeduse community hub that's a vibrant fusion of industrial design and community-centric spaces.

time-read
2 dak  |
September 2024
SHAPING THE FUTURE OF WORKSPACES
Commercial Design

SHAPING THE FUTURE OF WORKSPACES

Understanding the evolving dynamics of workplace design and operations.

time-read
3 dak  |
September 2024
CHANGING SHAPE
Commercial Design

CHANGING SHAPE

Five of the biggest breakthrough innovations redefining the fit-out industry

time-read
5 dak  |
September 2024
NAVIGATING THE START-UP OCEAN
Commercial Design

NAVIGATING THE START-UP OCEAN

Essential tips for founders setting sail

time-read
3 dak  |
September 2024
CREATING A SANCTUARY FOR WOMEN AND CHILDREN
Commercial Design

CREATING A SANCTUARY FOR WOMEN AND CHILDREN

Designed by Architecture Dialogue, the Nirbhaya Centre in Bengaluru sets a new benchmark in creating secure, welcoming spaces for women and children, blending innovative design with sustainability and community-focused principles

time-read
4 dak  |
September 2024